Used in the Eastern Daily Press Transport -- Trains Diesel train at Wisbech Station The Duputy Town Mayor of Wisbech, Mr Fedor Rikovsky waves goodbye to the first passenger train to leave the town for ten years Used in the Eastern Daily Press "Down Memory Lane" 16 February, 2005 Dated -- 23 September 1978 Photograph -- c10564

Tuesday, March 11, 2014
5:37 PM

The latest cost estimate for a new station in Wisbech has rocketed by more than £40m - but leaders still insist the case is the “strongest in a generation” and they can “make it happen”.

To send a link to this page to a friend, you must be logged in.

The latest cost estimate for a new station in Wisbech has rocketed by more than £40m - but leaders still insist the case is the “strongest in a generation” and they can “make it happen”.

At a rail summit in London, transport minister Stephen Hammond, Network Rail, train operating firm Greater Anglia and politicians, were told that reinstating the line and building a station in Wisbech could cost £52.6m, including a £15.6m bridge over the A47, while the bill for an out of town station south of the A47 would be £31m.

The original estimate for the project was £12m.

But North-East Cambridgeshire MP Stephen Barclay, who organised the summit, insisted that the “more refined costs” were a key sign of the maturity of the programme.

He said: “The costs going up is a sign of the more detailed work and more serious engagement in this project. Whilst the costs have shot up, what is clear is that the benefits have also shot up, and in my view significantly more than the costs. Instead of looking at who today would travel from Wisbech to March, we are looking at who would make that journey if the rail line was in place. That is a key difference.”

He added the case for the new rail station was the strongest it had been for a generation.

Alan Melton, leader of Fenland District Council, said he had only been told about the huge increase in costs yesterday, but had not been surprised.

He said it was vital that the partnership “get the figures right”, adding that he did not want a repeat of the Cambridge guided bus route project where costs had spiralled.

But Mr Melton, who was one of the last to use the line before it closed in 1968, said: “It has been many years we have been talking about this, and at last I get the sense that things are starting to work.
“We all recognise that the Cambridgeshire economy is unbalanced. We want to push some of that opportunity and growth to the North and the only way you are going to do that is through better infrastructure. I feel very optimistic after this meeting. There is a feeling we can make this happen,” he added.

Graham Nix, chief executive of the Greater Cambridgeshire Greater Peterborough local enterprise partnership (Lep), will be submitting a bid to the Government’s £2bn Local Growth Fund - which will allocated money to Leps through a “dragons den” style competition.

He said that the Wisbech Rail project - which would be part of the Lep’s bid - would be a good scheme in principle.

But all the leaders agreed that a great deal of work would need to be done in the next few weeks before the March 31st deadline for the fund.

Mr Barclay said that funding for the rail line could also come from the “significant housing proposals in Wisbech” through developer money for infrastructure as part of a planning deal - known as Section 106, which he said had been talked about in a “high level position.”

“There is significant work still to do. That won’t stop on March 31.”

Cambridgeshire County Council commissioned a study to consider capital costs of reinstating the line between March and Wisbech, following on from the 2012 Atkins Study, which concluded that the case for a light rail service from March to Wisbech, looked more promising.

Cambridgeshire County Council said the capital costs study was being finalised and it considered costs of reinstating the line for two possible options– a station in Wisbech and a station to the south of the town and the A47.

It said that the estimated potential cost of upgrading the line plus a station in Wisbech was £37m, and the cost of an A47 bridge was £15.6m.

While costs for upgrading the line with a station south of the A47 were estimated at £31m.

The study is expected to be published within a week.

7 comments

  • Looking at it another way John, this would take pressure off some of the East Cambs villages and make a rail commute to Peterborough ( and on to London) or more especially Cambridge feasible. There are limited areas suitable for construction in the East Cambs area and housing prices are rocketing way above those in the Wisbech area. Upgrading the whole Ely to Peterborough line, making all trains stop at March and re opening the Wisbech to March line would benefit Norfolk and the Fens.

    Report this comment

    Daisy Roots

    Wednesday, March 12, 2014

  • I have to agree, there are a lot better things to spend all that money on. I bet there isn't any copper wire left although the tracks are there.

    Report this comment

    Sweet cheeks

    Wednesday, March 12, 2014

  • If a station on the south side of the A47 is an option then my orchards are right on the juction of the A47 and Existing Trackbed. I would be very happy to offer the site for the project.... That should help keep costs down a lot.. all that would be needed is a roundabout, perhaps near the former crossing point on the A47.

    Report this comment

    martinday

    Wednesday, March 12, 2014

  • If a station on the south side of the A47 is an option then my orchards are right on the juction of the A47 and Existing Trackbed. I would be very happy to offer the site for the project.... That should help keep costs down a lot.. all that would be needed is a roundabout, perhaps near the former crossing point on the A47.

    Report this comment

    martinday

    Wednesday, March 12, 2014

  • Cancel HS2 and you could have an upgrade to the A47 and this and lots more besides.

    Report this comment

    Rich Hartt

    Wednesday, March 12, 2014

  • What a waste of tax payers money - if this amount of funding is available, it should be spent upgrading the A47

    Report this comment

    Norfolk John

    Tuesday, March 11, 2014

  • If a station on the south side of the A47 is an option then my orchards are right on the juction of the A47 and Existing Trackbed. I would be very happy to offer the site for the project.... That should help keep costs down a lot.. all that would be needed is a roundabout, perhaps near the former crossing point on the A47.

    Report this comment

    martinday

    Wednesday, March 12, 2014

The views expressed in the above comments do not necessarily reflect the views of this site

ADVERTISEMENT

ADVERTISEMENT

Homes24
Jobs24
Drive24
LocalSearch24
MyDate24
MyPhotos24
FamilyNotices24
Weddingsite

Click here to read more of our digital publications
Book my advert Fenland Enterprise Buisness Awards Paper delivery enquiries Retailers List

ADVERTISEMENT

ADVERTISEMENT