Multimillion pound upgrade to Ely North Junction “will definitely go ahead”, says Norfolk MP

PUBLISHED: 12:33 12 October 2017

South West Norfolk MP Elizabeth Truss led a delegation of MPs and rail officials to meet with transport secretary Chris Grayling. Picture: Fiona Walker

South West Norfolk MP Elizabeth Truss led a delegation of MPs and rail officials to meet with transport secretary Chris Grayling. Picture: Fiona Walker

Archant

Transport secretary Chris Grayling has given his commitment into making the Ely North junction upgrade a priority for the Department for Transport.

South West Norfolk MP Elizabeth Truss led a delegation of MPs and officials from local enterprise partnerships (LEPs) to see the minister yesterday (October 11).

Speaking after the meeting, Ms Truss said: “The transport secretary Chris Grayling agreed with us that the Ely Area Enhancement Programme is a priority and he wants to push ahead in Control Period 6 (CP6) with the upgrade.

“This is fantastic news, we have been campaigning for years for this and it will definitely be going ahead.

“One of the key aspects is to ensure the scheme is properly costed by Network Rail and the LEPs agreed to provide every assistance with this. Once the costings are finalised this will determine when in CP6 work starts.

“I am delighted that the transport secretary fully understood all the points we raised and that he has given this commitment today to see the work done in CP6 2019-2024.

“This will be an incredible boost to the region and the UK as a whole, investing in key infrastructure that will really transform rail travel in Norfolk.”

Chairman of the Fen Line Users Association and West Norfolk councillor Colin Sampson said: “As things stand we will get that work done between 2019 and 2024.

“We need to keep the pressure from now on so that everybody realises we mean business.

“We have achieved everything at this stage that we could’ve wished for.”

The cost of the project will become known once an £8.8m feasibility study into the scheme has been completed within the next few months.

The study is being carried out by Network Rail to determine the design of the scheme and how much it will cost before it can be considered for funding.

The study is partly funded by Greater Cambridge/Peterborough and New Anglia LEPs, both contributing £3.3m each, with the remaining £2.2m provided by the Strategic Freight Network.

Doug Field, chairman of New Anglia LEP, said: “We are delighted that the secretary of state has confirmed the case for improvements at Ely North is compelling and a priority for Government.

“It will bring huge improvements for passengers in Norfolk, Suffolk and Cambridgeshire. Also services connecting the UK’s busiest container port at Felixstowe with the Midlands and the North will be greatly enhanced.

“This project will deliver jobs and economic growth for the East.”

The project had previously failed to gain additional funding in 2015 as officials had underestimated how much it would cost - calculating it at £35m.

Once the funding has been secured work could begin in 2020, bringing more frequent services including half-hourly trains between King’s Lynn and London.

More news stories

31 minutes ago

There are calls for the railway line to King’s Lynn to be dualled as proposed timetable changes will leave passengers facing longer journey times.

51 minutes ago

A boot full of goodies has been donated to the rescue animals at RSPCA at Block Fen thanks to a car dealership.

13:29

2017 has been a year of highs and lows across Fenland – and it’s certainly been a busy one for our photographer Ian Carter, who has braved all weathers to capture the year on camera. Here are just some of the stories he has snapped along the way.

13:26

Students worked hard to raise the highest total yet from a non uniform day and cake sale.

Most read stories

HOT JOBS

Show Job Lists

HOT JOBS

Show Job Lists

Digital Edition

Image
Read the Cambs Times e-edition E-edition

Newsletter Sign Up

Sign up to receive our regular email newsletter