County council to deliver three road improvements across Fenland at a cost of �210,000

THREE Fenland roads are set for a �210,000 make over as part of a county council package of improvements.

The roads will be repaired by the county council this month and the first to benefit will be Highside, Gorefield.

Work will start on September 6 and is expected to take a week: the road will be closed with signed diversion in operation once work has started.

On September 11 work will begin, for a week, on Binnimoor Road in March. This is a no through road.

Westmoor Drove, Littleport will be the final road to be repaired by the council. Work will start from September 20 and is expected to be finished by September 23. Access to properties will remain with a signed diversion in operation.


You may also want to watch:


“Drivers are warned that disruption to traffic will occur and people should avoid or allow extra time for their journey around the sites,” said a council spokesman.

Most Read

Become a Supporter

This newspaper has been a central part of community life for many years. Our industry faces testing times, which is why we're asking for your support. Every contribution will help us continue to produce local journalism that makes a measurable difference to our community.

Become a Supporter
Comments powered by Disqus