THREE Fenland roads are set for a �210,000 make over as part of a county council package of improvements.
The roads will be repaired by the county council this month and the first to benefit will be Highside, Gorefield.
Work will start on September 6 and is expected to take a week: the road will be closed with signed diversion in operation once work has started.
On September 11 work will begin, for a week, on Binnimoor Road in March. This is a no through road.
Westmoor Drove, Littleport will be the final road to be repaired by the council. Work will start from September 20 and is expected to be finished by September 23. Access to properties will remain with a signed diversion in operation.
“Drivers are warned that disruption to traffic will occur and people should avoid or allow extra time for their journey around the sites,” said a council spokesman.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules here